Cases

實績案例_南化給水廠

Taiwan Water Corporation Nanhua Water Supply Plant

Environment Introduction:

  • Location is in Nanhua water purification plant, a total of 8 sets of sedimentation equipment as picture 1, and a total of 8 drainage tanks are surrounded.
  • 2 sets 3HP pumps are installed in each slurry drainage tank originally, a total 16 sets 3HP pumps. Previously have been replaced to total 3 sets 10HP pumps at 3 locations, this case to replace total 5 sets 10HP pumps at the other five drainage tanks.


Requirement Explanation:

  1. Due to the high viscosity of the slurry, the original 3HP pump will stop operate by slurry, so we need to replace to 10HP pump.
  2. All water in the sedimentation tank needs to be drained when maintaining the equipment, the original 3HP pump is unable to drain in time, so it needs to replace to 10HP pump.
  3. As the water volume increases in the rainy season, the original 3HP pump is unable to drain in time, so it needs to replace to 10HP pump.


Installation Model:

  • AS-3105/3Φ/440V total 5 sets


興達室內煤場之排水系統案

Taipower Xingda Power Plant

Environment Introduction:

  • The above equipment is installed at a total of 2 Xinda new indoor coal yards to offer more power to fire power plants.


Requirement Explanation:

  • The draining system is designed for a new coal yard, a total two catchment in each coal yard. 2 sets 3HP are installed in each catchment which can drain water in time when raining or flood.


Installation Model:

  • TOS-B-333*440V*8 sets


澎湖百世多麗酒店

Penghu Pescadores Hotel

Environment Introduction:

  1. This case is the sewage treatment project of Penghu Pescadores hotel.
  2. This project is divided into two areas and designed by the grading process to achieve sewage treatment function in each tank.


Requirement Explanation:

  • The above equipment is installed in a tank of initial sinking, adjustment, final sinking, filtering, circulation, intermediate, draining...etc. according to a different function.


Installation Model:

  1. TOS-B-333*6 sets
  2. TOS-B-353*2 sets (B Series Non-Clog Sewage Submersible Pump with Auto Lifting Device)


國防部鳳山協和新村

Ministry of National Defense Fengshan Xiehe Xincun

Environment Introduction:

  1. This case is a dependent village sewage reconstruction project of the ministry of national defense Fengshan Xiehe Xincun.
  2. This project is divided into four areas and designed by the grading process to achieve sewage treatment function in each tank.


Requirement Explanation:

  • The above equipment is installed in a tank of initial sinking, adjustment, final sinking, filtering, circulation, intermediate, draining...etc. according to a different function.


Installation Model:

  • TOS-B-312*4 sets
  • TOS-B-323*8 sets
  • TOS-B-333*4 sets
  • TOS-B-353*8 sets
  • TOS-B-3754*4 sets (B Series Non-Clog Sewage Submersible Pump with Auto Lifting Device)


國防部高山頂營區

Ministry of National Defense Alpine Top Campsite

Environment Introduction:

  1. This case is the phase I and phase II reconstruction project of ministry of national defense alpine top campsite.
  2. This project is divided into eight areas and designed by the grading process to achieve sewage treatment function in each tank.


Requirement Explanation:

  • The above equipment is installed in regulating、drainage tank.


Installation Model:

  • TOS-B-323*58 sets
  • TOS-B-3052*44 sets(B Series Non-Clog Sewage Submersible Pump with Auto Lifting Device)


台灣師大學生宿舍大樓

Taiwan Normal University Student Dormitory

Environment Introduction:

  • This case is sewage water improvement project of a student dormitory in Taiwan Normal University student dormitory


Requirement Explanation:

  • The above equipment is installed in regulating、drainage tank according to a different function.


Installation Model:

  • TOS-B-312*6 sets
  • TOS-B-333*2 sets (B Series Non-Clog Sewage Submersible Pump with Auto Lifting Device)


交通大學田家炳教育中心

Chiao Tung University Education Center

Environment Introduction:

  1. This case is an education center's new building project at Chiao Tung University.
  2. This project is designed by the grading process to achieve sewage treatment function in each tank.


Requirement Explanation:

  • The above equipment is installed in regulating、drainage tank.


Installation Model:

  1. TOS-B-3052*3 sets
  2. TOS-B-323*2 sets (B Series Non-Clog Sewage Submersible Pump with Auto Lifting Device)


新店美麗新世界新建案

Xindian New Building Project

Environment Introduction:

  1. This case is a sewage treatment project of Xindian New Building.
  2. This project is divided into three areas and designed by the grading process to achieve sewage treatment function in each tank.


Requirement Explanation:

  • The above equipment is installed in a tank of initial sinking, adjustment, final sinking, filtering, circulation, intermediate, draining...etc. according to a different function.


Installation Model:

  • TOS-B series 0.5HP*4 sets
  • TOS-B series 1HP*11 sets
  • TOS-B series 2HP*4 sets
  • TOS-B series 3HP*6 sets (B Series Non-Clog Sewage Submersible Pump with Auto Lifting Device)